Kingsley Beverages
Turnkey Water Treatment Solution for New Can Manufacturing Facility

When Kingsley Beverages decided to install a new can line they contracted Stolle, a global supplier of can manufacturing equipment and plants for a turnkey project in South Africa. In turn, Stolle subcontracted AllWater Technologies to conceptualise, design, create, oversee, and manage the build of the entire water treatment system.

The Challenge

The water treatment system required a reliable system to produce water of <10μS/cm for production and a wastewater treatment solution to consistently achieve local discharge consent limits, including low levels of Fluoride.

Requirements:

  • RO water quality: <10 μS/cm
  • RO serviceable water rate: 8 cubic metres per hour
  • Effluent discharge rate: 10 cubic metres per hour

Infrastructure

  • AllWater coordinated closely with Stolle to design and build the infrastructure, including providing layout design. load bearing information and suggestions for area containment.
  • The layout design included a dedicated tank farm with access gantry to reaction tank area and filter press, pure water generation area with clear delineation from wastewater treatment area, ergonomic flow path reducing the need for pumping wherever possible and ease of forklift access to powder reagent make-up system.

Reverse Osmosis

  • To enhance water quality and increase overall system recovery, it was decided to operate two RO units in series. Twin pass RO system designed with 2 identical plants, either of which can be operated in the ‘lead’ or ‘lag’ position, or independently, offering a high-level of flexibility and operational security.
  • Operating the units in series ensured exceptionally good water quality and increased the overall recovery level of the system, providing maximum output and efficiency.

Wastewater Treatment

  • Two reception tank system, able to accommodate day-to-day rinse water, periodic discharge of higher strength concentrates and also emergency holding capacity.
  • Two stages of reaction tanks and settlers, all joined via gravity, in order to achieve low Fluoride discharge consent limit.
  • Continuous outfall monitoring including auto-divert and retreatment for out-of-specification effluent.

The Chemistry

Stage 1: Lime Dosing
  • Lime is dosed into the effluent stream to facilitate the precipitation of Calcium Fluoride. This process effectively reduces Fluoride levels to a reasonably low level and neutralises the acidic nature of the effluent.
  • Lime dosing is a cost-effective process that eliminates a large amount of Fluoride from the water.
Stage 2: Fluoride Precipitation
  • A specific Fluoride removal chemistry is introduced into the effluent within the reaction tank system. This proprietary targets Fluoride specifically, facilitating its removal from the effluent stream.
  • The addition of Fluoride removal chemistry achieves the discharge limit of <5 mg/litre Fluoride.

Further Support

  • An installation manager from AllWater supervised on-site activities, ensuring adherence to design specifications and quality standards.
  • Commissioning engineers were dispatched to the site to commission the unit, verifying that all systems met the required performance standards.
  • Comprehensive training was provided to the local personnel, covering all aspects of the system’s operation, maintenance, and troubleshooting.
  • Continuous remote support is offered to address any issues that may arise and to assist with system optimisation.

Conclusion

The successful completion of the Kingsley can factory water treatment system highlights AllWater Technologies’ capability to deliver effective turnkey solutions. By meeting stringent water quality and effluent discharge requirements through innovative design and advanced chemistry, we ensured efficient and compliant operations. Our ongoing support and thorough training empowered the local team to maintain optimal performance. This project demonstrates our commitment to excellence and our ability to handle complex water treatment challenges for clients worldwide.

Kingsley-Logo-No-Background

"We have been very happy with AllWater’s professionalism and response times when we have needed help with the plant. The staff are all very helpful and knowledgeable and we are very satisfied with the service provided."

Jamie Davies

Turnspeed

"We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm."

Steve Silk MBE

Marshall Aerospace

"We have built a good relationship with AllWater and continue to enjoy service contracts with them. They know what they’re doing and we’re always happy with their service"

Andy Best

Production Director - Vertik-Al

"We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm’"

Amelia

Production Manager

"AllWater Technologies installed their pure water system in our premises to replace our old system which went into retirement. The level of service and maintenance that AllWater are giving us will ensure that we get the quality of product and the length of service we are looking for out of our plant. Their level of service is excellent."

John Malone

excel gs ltd

"Thank you for all your support. I have to say that I am really impressed with All Water approach to provide a really good service. Thank you again."

Radu Vitanescu

Liberty Engineering

"AllWater have provided great service, specialist advice and an effective waste water treatment solution for our site."

Paul Pearcy

Warburtons

"AllWater have always delivered us a great service and are equally competent maintaining existing kit or installing new. They’re friendly and reliable and, perhaps most importantly, trustworthy."

Phil Parkinson

Joseph Holt

"AWT professional service allows our site to run with minimal downtime when unplanned breakdowns happen. AWT service is invaluable in maintaining our production lines throughout."

Adam Cook

Qsil

"The person was very polite and explained everything in detail. Report was typed and easy to understand."

Richard Fox

London and Brighton Plating

"We are more than satisfied with the level of service we receive from everyone at AWT. Excellent work, Thank you!"

Daniel Holden

Karas Plating

"AllWater Technologies provide an exceptional level of knowledge and support, and we cannot fault their service and commitment. The team consistently exceed expectations and although others may offer a cheaper alternative, we have every confidence that they could not offer better!"

Eric Allen

Albumedix LTD

"By using AWT we know that our plant and equipment is being maintained to the highest standard using the expertise and knowledge that we find second to none. When issues arise it is paramount that we can resolve these issues promptly; AWT are always there to support us."

Allen Staunton

Creganna Medical

"Using All Water Technologies has been a breath of fresh air. Their attentive service from the first call through to delivery completion, has made the management of our water treatment plant very easy indeed. We wash over 2.5 million items of tableware for the event industry every year, working at some of the UK’s most prestigious events, so having peace of mind over our washing operation is essential. I would recommend AWT to anyone’"

Joe Nisbet

Jongor Hire

"AWT offered Rimex a bespoke solution to our water softening and storage requirements. They took charge and managed the project efficiently and effectively from the very beginning. I am delighted with the outcome and I will continue to use AWT for preventative maintenance and any other future projects."

Daniel Meakin

Rimex Metals

"All went very well with the plant being well finished, installation being of a high standard and all works being completed on time and to specification."

Dom Oughton

Optimum

"We’ve been working with the AllWater team for eight years and they have always been attentive to our needs. AllWater redesigned our borehole system, transforming it into a robust and reliable plant whilst helping us improve water recovery and achieve significant water savings. We’ve depended on this system and their technical guidance for many years now and will continue to do so. Their work helps give us confidence and they are a partner we know we can trust."

Stephen Shields

Huntapac - Technical & Sustainability Director

"At Butcombe, AllWater Technologies have been servicing the water treatment systems in our brewery for over 10 years. They are always at hand when we need them and all very friendly to deal with, and callouts are always made in a very timely manner. They have kept our beer flowing having never let us down. A great company with a quality reliable service."

Simon Court

Brewer - Butcombe Brewing Co.

Get in Touch with AllWater Technologies

We’re here to help with all your water treatment needs. Whether you have questions about our services, want to discuss a project, or need support, our team is ready to assist you. Fill out the form for general enquiries, or you are welcome to email direct or give us a call.

AllWater House

Unit 2,

Cheddar Business Park,

Wedmore Road,

Cheddar

BS27 3EB

Opening hours

Mon-Fri: 08:30-17:30 (GMT)


    Case Study A Smooth Transition:
    Enabling Vertik-Al's Chromium-Free Future

    Water Treatment Solutions to Overcome New REACH Prohibition of Hexavalent Chromium, Negotiate Space Constraints and Maintain Production Output

    Project Overview

    Vertik-Al, a leading provider of vertical and horizontal Aluminium powder coating for the architectural Aluminium industry, faced a critical challenge when European regulations (REACH) prohibited the use of Hexavalent Chromium in their pre-treatment process. To comply with regulations while maintaining consistent production efficiency, Vertik-Al needed a reliable water supply with stringent quality requirements.

    • INDUSTRY: Multi-industry Powder Coating Manufacturing
    • PROBLEM: Transition from Hexavalent Chromium to Chromium-Free Pre-Treatment
    • IMPLEMENTED SOLUTION: Water Supply with <30 μS/cm Quality

    The Problem

    The transition from a Hexavalent Chromium to a Chromium-free process required a large volume of water with a quality level below 30 μS/cm to ensure effective pre-treatment. Restrictive space at VertikAl’s facility posed significant hurdles for installing the required water treatment systems. Additionally, maintaining uninterrupted production during the transition was crucial for Vertik-Al to meet customer demands and ensure operational continuity.

    The Result

    The integrated water treatment system provided by AllWater enabled Vertik-Al to meet stringent purity standards for Chromium-free processes, ensuring compliance with REACH regulatory requirements whilst enhancing operational efficiency. Despite space constraints and existing infrastructure limitations, the seamless integration of the new water treatment system allowed Vertik-Al to maintain uninterrupted production, eliminating downtime and sustaining productivity. By leveraging AllWater’s expertise and innovative solutions, Vertik-Al successfully navigated the transition to Chromium-free manufacturing processes, demonstrating a commitment to regulatory compliance and operational excellence. 

    The Solution

    • Space Optimisation: AllWater Technologies Ltd and Vertik-Al devised a solution to optimise space utilisation. Existing bulk chemical storage tanks, including redundant units, were removed and replaced with chemical day tanks, which in turn were fed by gravity from IBCs

    • Customised Water Treatment System: AllWater coordinated with Vertik-Al to keep the existing DI plant operational whilst space was cleared for a new Duplex DI plant. Once the new plant was successfully commissioned the old plant was removed from service, refurbished, and once more recommissioned , utilising a new PLC/HMI driven control system which now encompasses all 4 ion exchange DI streams.

    • Monitoring System: Implementation of advanced monitoring technologies, including realtime monitoring of chemical usage and system performance, provided Vertik-Al with enhanced visibility and control over their water treatment processes, facilitating proactive maintenance and optimisation.

    "We have been very happy with AllWater’s professionalism and response times when we have needed help with the plant. The staff are all very helpful and knowledgeable and we are very satisfied with the service provided."

    Jamie Davies

    Turnspeed

    "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm."

    Steve Silk MBE

    Marshall Aerospace

    "We have built a good relationship with AllWater and continue to enjoy service contracts with them. They know what they’re doing and we’re always happy with their service"

    Andy Best

    Production Director - Vertik-Al

    "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm’"

    Amelia

    Production Manager

    "AllWater Technologies installed their pure water system in our premises to replace our old system which went into retirement. The level of service and maintenance that AllWater are giving us will ensure that we get the quality of product and the length of service we are looking for out of our plant. Their level of service is excellent."

    John Malone

    excel gs ltd

    "Thank you for all your support. I have to say that I am really impressed with All Water approach to provide a really good service. Thank you again."

    Radu Vitanescu

    Liberty Engineering

    "AllWater have provided great service, specialist advice and an effective waste water treatment solution for our site."

    Paul Pearcy

    Warburtons

    "AllWater have always delivered us a great service and are equally competent maintaining existing kit or installing new. They’re friendly and reliable and, perhaps most importantly, trustworthy."

    Phil Parkinson

    Joseph Holt

    "AWT professional service allows our site to run with minimal downtime when unplanned breakdowns happen. AWT service is invaluable in maintaining our production lines throughout."

    Adam Cook

    Qsil

    "The person was very polite and explained everything in detail. Report was typed and easy to understand."

    Richard Fox

    London and Brighton Plating

    "We are more than satisfied with the level of service we receive from everyone at AWT. Excellent work, Thank you!"

    Daniel Holden

    Karas Plating

    "AllWater Technologies provide an exceptional level of knowledge and support, and we cannot fault their service and commitment. The team consistently exceed expectations and although others may offer a cheaper alternative, we have every confidence that they could not offer better!"

    Eric Allen

    Albumedix LTD

    "By using AWT we know that our plant and equipment is being maintained to the highest standard using the expertise and knowledge that we find second to none. When issues arise it is paramount that we can resolve these issues promptly; AWT are always there to support us."

    Allen Staunton

    Creganna Medical

    "Using All Water Technologies has been a breath of fresh air. Their attentive service from the first call through to delivery completion, has made the management of our water treatment plant very easy indeed. We wash over 2.5 million items of tableware for the event industry every year, working at some of the UK’s most prestigious events, so having peace of mind over our washing operation is essential. I would recommend AWT to anyone’"

    Joe Nisbet

    Jongor Hire

    "AWT offered Rimex a bespoke solution to our water softening and storage requirements. They took charge and managed the project efficiently and effectively from the very beginning. I am delighted with the outcome and I will continue to use AWT for preventative maintenance and any other future projects."

    Daniel Meakin

    Rimex Metals

    "All went very well with the plant being well finished, installation being of a high standard and all works being completed on time and to specification."

    Dom Oughton

    Optimum

    "We’ve been working with the AllWater team for eight years and they have always been attentive to our needs. AllWater redesigned our borehole system, transforming it into a robust and reliable plant whilst helping us improve water recovery and achieve significant water savings. We’ve depended on this system and their technical guidance for many years now and will continue to do so. Their work helps give us confidence and they are a partner we know we can trust."

    Stephen Shields

    Huntapac - Technical & Sustainability Director

    "At Butcombe, AllWater Technologies have been servicing the water treatment systems in our brewery for over 10 years. They are always at hand when we need them and all very friendly to deal with, and callouts are always made in a very timely manner. They have kept our beer flowing having never let us down. A great company with a quality reliable service."

    Simon Court

    Brewer - Butcombe Brewing Co.

    Tailored Water Treatment Solutions for Your Sector

    We’re here to help with all your water treatment needs. Whether you have questions about our services, want to discuss a project, or need support, our team is ready to assist you. Fill out the form for general enquiries, or you are welcome to email direct or give us a call.

    AllWater House

    Unit 2,

    Cheddar Business Park,

    Wedmore Road,

    Cheddar

    BS27 3EB

    Opening hours

    Mon-Fri: 08:30-17:30 (GMT)


      Case Study Marshall Aerospace
      Transformative Solutions

      AllWater Technologies Enables Relocation with Recovery DI for Marshall Aerospace

      Case Study Overview

      Marshall Aerospace, a leading MRO and Aerospace component manufacturing facility, faced a critical challenge when relocation there Manufacturing and Special Processes facility to a new site, including the need to manage operational costs and environmental impact efficiently.

      • Industry: Specialised Engineering for Aerospace Components
      • Problem: Need for Efficient Relocation Due to Planning Permission Requirements
      • Implemented Solution: Advanced Water Recovery DI System

      The Challenge

      The primary challenge for Marshall Aerospace was the imperative to relocate due to planning permission requirements at their existing location. This necessitated the exploration of efficient and environmentally sustainable water treatment solutions for their new site, whilst managing operational costs effectively.

      The Solution

      • Mass Balance Analysis: Conducted to estimate contaminant levels, forming the foundation for designing an effective water recovery strategy.
      • Water Recovery DI System: Utilising advanced ion exchange resin technology to capture and treat contaminants.
      • RO Water Makeup: Recommending the use of Reverse Osmosis (RO) water for makeup to extend the service life of the DI system and reduce operational costs.

      The Result

      • Water Quality: Consistently cleaning water to 1.00 μS/cm.
      • Waste Reduction: Significantly reduced the volume of hazardous waste, aligning with responsible manufacturing practices.
      • Lowered Financial Cost: Successfully minimised environmental impact and reduced operational costs by strategically using RO water.

      Conclusion

      The successful implementation of the Water Recovery DI System by AllWater Technologies addressed Marshall Aerospace’s primary challenge of relocating their Manufacturing and Special Processes facility while meeting planning permission requirements. The implementation of the Water Recovery DI System and RO water helped achieve reductions in environmental impact, enhanced operational efficiency, and reduced financial costs.

      New-Website-Case-Studies-Marshall-Aerospace

      "We have been very happy with AllWater’s professionalism and response times when we have needed help with the plant. The staff are all very helpful and knowledgeable and we are very satisfied with the service provided."

      Jamie Davies

      Turnspeed

      "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm."

      Steve Silk MBE

      Marshall Aerospace

      "We have built a good relationship with AllWater and continue to enjoy service contracts with them. They know what they’re doing and we’re always happy with their service"

      Andy Best

      Production Director - Vertik-Al

      "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm’"

      Amelia

      Production Manager

      "AllWater Technologies installed their pure water system in our premises to replace our old system which went into retirement. The level of service and maintenance that AllWater are giving us will ensure that we get the quality of product and the length of service we are looking for out of our plant. Their level of service is excellent."

      John Malone

      excel gs ltd

      "Thank you for all your support. I have to say that I am really impressed with All Water approach to provide a really good service. Thank you again."

      Radu Vitanescu

      Liberty Engineering

      "AllWater have provided great service, specialist advice and an effective waste water treatment solution for our site."

      Paul Pearcy

      Warburtons

      "AllWater have always delivered us a great service and are equally competent maintaining existing kit or installing new. They’re friendly and reliable and, perhaps most importantly, trustworthy."

      Phil Parkinson

      Joseph Holt

      "AWT professional service allows our site to run with minimal downtime when unplanned breakdowns happen. AWT service is invaluable in maintaining our production lines throughout."

      Adam Cook

      Qsil

      "The person was very polite and explained everything in detail. Report was typed and easy to understand."

      Richard Fox

      London and Brighton Plating

      "We are more than satisfied with the level of service we receive from everyone at AWT. Excellent work, Thank you!"

      Daniel Holden

      Karas Plating

      "AllWater Technologies provide an exceptional level of knowledge and support, and we cannot fault their service and commitment. The team consistently exceed expectations and although others may offer a cheaper alternative, we have every confidence that they could not offer better!"

      Eric Allen

      Albumedix LTD

      "By using AWT we know that our plant and equipment is being maintained to the highest standard using the expertise and knowledge that we find second to none. When issues arise it is paramount that we can resolve these issues promptly; AWT are always there to support us."

      Allen Staunton

      Creganna Medical

      "Using All Water Technologies has been a breath of fresh air. Their attentive service from the first call through to delivery completion, has made the management of our water treatment plant very easy indeed. We wash over 2.5 million items of tableware for the event industry every year, working at some of the UK’s most prestigious events, so having peace of mind over our washing operation is essential. I would recommend AWT to anyone’"

      Joe Nisbet

      Jongor Hire

      "AWT offered Rimex a bespoke solution to our water softening and storage requirements. They took charge and managed the project efficiently and effectively from the very beginning. I am delighted with the outcome and I will continue to use AWT for preventative maintenance and any other future projects."

      Daniel Meakin

      Rimex Metals

      "All went very well with the plant being well finished, installation being of a high standard and all works being completed on time and to specification."

      Dom Oughton

      Optimum

      "We’ve been working with the AllWater team for eight years and they have always been attentive to our needs. AllWater redesigned our borehole system, transforming it into a robust and reliable plant whilst helping us improve water recovery and achieve significant water savings. We’ve depended on this system and their technical guidance for many years now and will continue to do so. Their work helps give us confidence and they are a partner we know we can trust."

      Stephen Shields

      Huntapac - Technical & Sustainability Director

      "At Butcombe, AllWater Technologies have been servicing the water treatment systems in our brewery for over 10 years. They are always at hand when we need them and all very friendly to deal with, and callouts are always made in a very timely manner. They have kept our beer flowing having never let us down. A great company with a quality reliable service."

      Simon Court

      Brewer - Butcombe Brewing Co.

      Get in Touch with AllWater Technologies

      We’re here to help with all your water treatment needs. Whether you have questions about our services, want to discuss a project, or need support, our team is ready to assist you. Fill out the form for general enquiries, or you are welcome to email direct or give us a call.

      AllWater House

      Unit 2,

      Cheddar Business Park,

      Wedmore Road,

      Cheddar

      BS27 3EB

      Opening hours

      Mon-Fri: 08:30-17:30 (GMT)


        Case Study A Smooth Transition:
        Enabling Vertik-Al's Chromium-Free Future

        Water Treatment Solutions to Overcome New REACH Prohibition of Hexavalent Chromium, Negotiate Space Constraints and Maintain Production Output

        Case Study Overview

        Vertik-Al, a leading provider of vertical and horizontal Aluminium powder coating for the architectural Aluminium industry, faced a critical challenge when European regulations (REACH) prohibited the use of Hexavalent Chromium in their pre-treatment process. To comply with regulations while maintaining consistent production efficiency, Vertik-Al needed a reliable water supply with stringent quality requirements.

        • INDUSTRY: Multi-industry Powder Coating Manufacturing
        • PROBLEM: Transition from Hexavalent Chromium to Chromium-Free Pre-Treatment
        • IMPLEMENTED SOLUTION: Water Supply with <30 μS/cm Quality

        The Problem

        The transition from a Hexavalent Chromium to a Chromium-free process required a large volume of water with a quality level below 30 μS/cm to ensure effective pre-treatment. Restrictive space at VertikAl’s facility posed significant hurdles for installing the required water treatment systems. Additionally, maintaining uninterrupted production during the transition was crucial for Vertik-Al to meet customer demands and ensure operational continuity.

        The Result

        The integrated water treatment system provided by AllWater enabled Vertik-Al to meet stringent purity standards for Chromium-free processes, ensuring compliance with REACH regulatory requirements whilst enhancing operational efficiency. Despite space constraints and existing infrastructure limitations, the seamless integration of the new water treatment system allowed Vertik-Al to maintain uninterrupted production, eliminating downtime and sustaining productivity. By leveraging AllWater’s expertise and innovative solutions, Vertik-Al successfully navigated the transition to Chromium-free manufacturing processes, demonstrating a commitment to regulatory compliance and operational excellence. 

        The Solution

        • Space Optimisation: AllWater Technologies Ltd and Vertik-Al devised a solution to optimise space utilisation. Existing bulk chemical storage tanks, including redundant units, were removed and replaced with chemical day tanks, which in turn were fed by gravity from IBCs

        • Customised Water Treatment System: AllWater coordinated with Vertik-Al to keep the existing DI plant operational whilst space was cleared for a new Duplex DI plant. Once the new plant was successfully commissioned the old plant was removed from service, refurbished, and once more recommissioned , utilising a new PLC/HMI driven control system which now encompasses all 4 ion exchange DI streams.

        • Monitoring System: Implementation of advanced monitoring technologies, including realtime monitoring of chemical usage and system performance, provided Vertik-Al with enhanced visibility and control over their water treatment processes, facilitating proactive maintenance and optimisation.

        "We have been very happy with AllWater’s professionalism and response times when we have needed help with the plant. The staff are all very helpful and knowledgeable and we are very satisfied with the service provided."

        Jamie Davies

        Turnspeed

        "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm."

        Steve Silk MBE

        Marshall Aerospace

        "We have built a good relationship with AllWater and continue to enjoy service contracts with them. They know what they’re doing and we’re always happy with their service"

        Andy Best

        Production Director - Vertik-Al

        "We needed a DI plant that is capable of producing the processing water to serve our Chemical Process lines twelve rinse tanks, 24 hrs a day, 7 days a week at a max of 20.00 μS/cm. The water plant is now consistently cleaning the water to 1.00 μS/cm’"

        Amelia

        Production Manager

        "AllWater Technologies installed their pure water system in our premises to replace our old system which went into retirement. The level of service and maintenance that AllWater are giving us will ensure that we get the quality of product and the length of service we are looking for out of our plant. Their level of service is excellent."

        John Malone

        excel gs ltd

        "Thank you for all your support. I have to say that I am really impressed with All Water approach to provide a really good service. Thank you again."

        Radu Vitanescu

        Liberty Engineering

        "AllWater have provided great service, specialist advice and an effective waste water treatment solution for our site."

        Paul Pearcy

        Warburtons

        "AllWater have always delivered us a great service and are equally competent maintaining existing kit or installing new. They’re friendly and reliable and, perhaps most importantly, trustworthy."

        Phil Parkinson

        Joseph Holt

        "AWT professional service allows our site to run with minimal downtime when unplanned breakdowns happen. AWT service is invaluable in maintaining our production lines throughout."

        Adam Cook

        Qsil

        "The person was very polite and explained everything in detail. Report was typed and easy to understand."

        Richard Fox

        London and Brighton Plating

        "We are more than satisfied with the level of service we receive from everyone at AWT. Excellent work, Thank you!"

        Daniel Holden

        Karas Plating

        "AllWater Technologies provide an exceptional level of knowledge and support, and we cannot fault their service and commitment. The team consistently exceed expectations and although others may offer a cheaper alternative, we have every confidence that they could not offer better!"

        Eric Allen

        Albumedix LTD

        "By using AWT we know that our plant and equipment is being maintained to the highest standard using the expertise and knowledge that we find second to none. When issues arise it is paramount that we can resolve these issues promptly; AWT are always there to support us."

        Allen Staunton

        Creganna Medical

        "Using All Water Technologies has been a breath of fresh air. Their attentive service from the first call through to delivery completion, has made the management of our water treatment plant very easy indeed. We wash over 2.5 million items of tableware for the event industry every year, working at some of the UK’s most prestigious events, so having peace of mind over our washing operation is essential. I would recommend AWT to anyone’"

        Joe Nisbet

        Jongor Hire

        "AWT offered Rimex a bespoke solution to our water softening and storage requirements. They took charge and managed the project efficiently and effectively from the very beginning. I am delighted with the outcome and I will continue to use AWT for preventative maintenance and any other future projects."

        Daniel Meakin

        Rimex Metals

        "All went very well with the plant being well finished, installation being of a high standard and all works being completed on time and to specification."

        Dom Oughton

        Optimum

        "We’ve been working with the AllWater team for eight years and they have always been attentive to our needs. AllWater redesigned our borehole system, transforming it into a robust and reliable plant whilst helping us improve water recovery and achieve significant water savings. We’ve depended on this system and their technical guidance for many years now and will continue to do so. Their work helps give us confidence and they are a partner we know we can trust."

        Stephen Shields

        Huntapac - Technical & Sustainability Director

        "At Butcombe, AllWater Technologies have been servicing the water treatment systems in our brewery for over 10 years. They are always at hand when we need them and all very friendly to deal with, and callouts are always made in a very timely manner. They have kept our beer flowing having never let us down. A great company with a quality reliable service."

        Simon Court

        Brewer - Butcombe Brewing Co.

        Get in Touch with AllWater Technologies

        We’re here to help with all your water treatment needs. Whether you have questions about our services, want to discuss a project, or need support, our team is ready to assist you. Fill out the form for general enquiries, or you are welcome to email direct or give us a call.

        AllWater House

        Unit 2,

        Cheddar Business Park,

        Wedmore Road,

        Cheddar

        BS27 3EB

        Opening hours

        Mon-Fri: 08:30-17:30 (GMT)